Founded in 1991, T BAILEY, INC is a diversified general contractor experienced in heavy-civil/industrial construction and heavy steel fabrication/structural fabrication. Our extensive experience in aboveground, field-erected fuel and water tank projects has established T BAILEY, INC. as a leader in the Northwest of safety, quality control, and project management. Regardless of the project, our commitment to quality, integrity, and value has earned us a history of strong customer satisfaction.
2016
With approximately 120,000 square feet of covered facilities designed to perform custom fabrication of heavy structural and plate products, our prime location in Anacortes, Washington gives us the opportunity to directly ship and receive oversized loads via barge, rail, or truck.
Our diverse fabrication capabilities include compliance to API, AWWA, AWS, UL, AISC, CWB and ASME codes including UL tanks, pressure vessels, AWWA and API shop and field erected tanks, water storage tanks, large diameter casings/caissons, penstock, water piping, breaching, exhaust stacks, and wind turbine towers, as well as performing timely and high-quality above ground steel tank repairs. In addition, we operate a state of the art SSPC QP3 Certified wheelabrating and paint facility for steel surface preparation and application of prime and finish paint systems.
T BAILEY, INC. is an AISC Certified Fabricator and has all three of the Sophisticated Paint Endorsements. We are also CWB certified and an SPFA Certified Pipe Fabricator.
Fort St John – AFDE
While fabrication was made easier thanks to T BAILEY, INC.’s state-of-the-art facility in Anacortes, the project did not end there. Each one of the sections had to be shipped to Fort St. John.
Santos Alaska
The Crowley tank project is one of the largest tank projects T BAILEY, INC. has undertaken. With four million pounds of steel being used and shipped to the project site, three tanks were constructed near Fairbanks, Alaska.
West Coast Reductions
The Crowley tank project is one of the largest tank projects T BAILEY, INC. has undertaken. With four million pounds of steel being used and shipped to the project site, three tanks were constructed near Fairbanks, Alaska.
Guam Project
The Crowley tank project is one of the largest tank projects T BAILEY, INC. has undertaken. With four million pounds of steel being used and shipped to the project site, three tanks were constructed near Fairbanks, Alaska.
ROC Equipment Hawaii Light Rail Casing Fabrication Project
T BAILEY INC. was brought on as a supplier to fabricate the drilled shaft casing for the new Honolulu Rail Transit Project (also called the Honolulu High-Capacity Transit Corridor Project).
Crowley Tank Construction
The Crowley tank project is one of the largest tank projects T BAILEY, INC. has undertaken. With four million pounds of steel being used and shipped to the project site, three tanks were constructed near Fairbanks, Alaska.
Seaside East Hills Reservoir Project
Seaside is a picturesque city that hugs the Oregon coast and hosts thousands of tourists and year-round residents. The City of Seaside embarked on a project to build a new high school as a tsunami evacuation location high on a hill overlooking the city.
Highline Mansion Hill Reservoir Relocation Project
T Bailey INC. was brought onto the Highline Mansion Hill Reservoir project as a general contractor to help Highline Water District relocate a large water reservoir.
Klamath Irrigation District Penstock Project
T BAILEY, INC. fabricated, coated and delivered approximately 786 LF of 119” diameter ½” thick steel pipe in various lengths ranging from 5’ L – 43’ L, including 3 elbow sections, 12 ring girders, 24 slide bearing / fixed bearing supports, trash rack structure and 215’ of catwalk.
Clear Air Force Base Fireguard Tanks
T BAILEY, INC. fabricated, coated and delivered approximately 786 LF of 119” diameter ½” thick steel pipe in various lengths ranging from 5’ L – 43’ L, including 3 elbow sections, 12 ring girders, 24 slide bearing / fixed bearing supports, trash rack structure and 215’ of catwalk.
Swift Dam Penstock and Bifurcation Project
T BAILEY, INC. fabricated, coated and delivered approximately 786 LF of 119” diameter ½” thick steel pipe in various lengths ranging from 5’ L – 43’ L, including 3 elbow sections, 12 ring girders, 24 slide bearing / fixed bearing supports, trash rack structure and 215’ of catwalk.
Lyons Ferry Straw Pulp Plant
T BAILEY, INC. fabricated, coated and delivered approximately 786 LF of 119” diameter ½” thick steel pipe in various lengths ranging from 5’ L – 43’ L, including 3 elbow sections, 12 ring girders, 24 slide bearing / fixed bearing supports, trash rack structure and 215’ of catwalk.
Fireguard® Tanks: How T BAILEY INC. Fabricated Disaster-Resistant Fuel Tanks For The Air Force
T BAILEY, INC. fabricated, coated and delivered approximately 786 LF of 119” diameter ½” thick steel pipe in various lengths ranging from 5’ L – 43’ L, including 3 elbow sections, 12 ring girders, 24 slide bearing / fixed bearing supports, trash rack structure and 215’ of catwalk.
Port Mann Bridge Piling
T BAILEY, INC. fabricated, coated and delivered approximately 786 LF of 119” diameter ½” thick steel pipe in various lengths ranging from 5’ L – 43’ L, including 3 elbow sections, 12 ring girders, 24 slide bearing / fixed bearing supports, trash rack structure and 215’ of catwalk.
Tesoro’s Avon Wharf Facility Steel Pile Cap Frames
T BAILEY, INC. fabricated, coated and delivered approximately 786 LF of 119” diameter ½” thick steel pipe in various lengths ranging from 5’ L – 43’ L, including 3 elbow sections, 12 ring girders, 24 slide bearing / fixed bearing supports, trash rack structure and 215’ of catwalk.
Water System Improvement Project – Vale, Oregon
T BAILEY, INC. fabricated, coated and delivered approximately 786 LF of 119” diameter ½” thick steel pipe in various lengths ranging from 5’ L – 43’ L, including 3 elbow sections, 12 ring girders, 24 slide bearing / fixed bearing supports, trash rack structure and 215’ of catwalk.
Port of Alaska Dock Piling Fabrication
T BAILEY, INC. fabricated, coated and delivered approximately 786 LF of 119” diameter ½” thick steel pipe in various lengths ranging from 5’ L – 43’ L, including 3 elbow sections, 12 ring girders, 24 slide bearing / fixed bearing supports, trash rack structure and 215’ of catwalk.
LAX People Mover Casing Fabrication
T BAILEY, INC. fabricated, coated and delivered approximately 786 LF of 119” diameter ½” thick steel pipe in various lengths ranging from 5’ L – 43’ L, including 3 elbow sections, 12 ring girders, 24 slide bearing / fixed bearing supports, trash rack structure and 215’ of catwalk.
Haines Water Reservoir Construction & Water Meter Project
The Oregon Department of Health put out an order for the town of Haines, Oregon, to redo their water meters and build a new water reservoir. The water meters hadn’t been refreshed since the 1990s and the town’s existing water tower had been built in 1910 — it was time for an update. T BAILEY…
Grand Mound Water Tank Fabrication & Construction
Thurston County approached T BAILEY INC. and requested that we build a new water storage tank for its Grand Mound community. The job site currently had a single water tank on it, but Thurston County wanted another one built to improve water flow and to increase fire protection for the growing residential area around the…
Woodinville Brookside Reservoir Improvement
Woodinville Water District requested bids on a tank improvement project for a Brookside neighborhood water reservoir. The aging reservoir was located in a residential area and serviced the homes and businesses around it, providing water and fire flow. Due to our decades-long work experience improving, restoring, and retrofitting field-erected tanks, T BAILEY INC. felt that…
Project Story: Firgrove Zone 2A Reservoir
Firgrove Mutual, a water utility company based out of Puyallup, requested bids for a reservoir and pumphouse project in Graham, Washington. We felt that our field erection crew was uniquely qualified to exceed Firgrove’s expectations on this project, so we submitted a competitive bid and got accepted. While T BAILEY INC. could have provided design…
Dutch Harbor 70,000-Gallon Fish-Oil Tanks
One (1) 95’-0” diameter x 60’ high 75,000 BBL Capacity, Three (3) 80’-0” diameter x 60’ high 53,000 BBL Capacity, and One (1) 36’-0” diameter x 32’ high 5800 BBL Capacity API 650 welded steel storage tanks with internal floating roofs constructed and painted in Tacoma, WA.
Shell Puget Sound Refinery – Degassing Drum Fabrication
T BAILEY, INC. fabricated, finish painted, and delivered a 14’-0” Dia. x 57’-0” long ASME Code pressure vessel for Shell’s Anacortes, WA refinery.
Westway Terminals Aberdeen, WA
4 each 80 BBL API 650 Storage Tanks 120′ diameter x 40′ high with internal floating roofs. This was a design/build project for a private developer. All 4 tanks were field erected in a five-month window to meet the client’s schedule to become operational.
Casing Gerald Desmond Bridge Replacement
T BAILEY, INC. fabricated approximately 72 pieces of oscillator casing in various sizes from 1500mm to 2500 mm in diameter in typical 24’ long sections provided in both 1” and 2” carbon steel wall thicknesses for the Gerald Desmond Bridge Replacement project located in Long Beach, CA.
Barge Load Out Facility
T BAILEY’s barge loadout facility is located on the Swinomish Channel within a mile of our March Point Road, Anacortes, WA fabrication shop. The barge shown above is 180’ in length and 45’ wide with 3 each 12’6” diameter x 44’ long pressure vessels loaded for shipment to Alaska.
USACE Centralized Fueling Station – Yakima, WA
T BAILEY, INC. performed site development including fuel containment and underground utilities to accommodate 3 new API 650 fuel tanks and 2 UL 142 fuel tanks.
North Water Reservoir – Gig Harbor, WA
A 2006 Steel Tank Institute Tank of the Year Award-winning 160’ft high x 53’d welded steel water tank with a self-supported seal welded knuckle roof. The site was located in a new housing development and had very limited access and the developer requested minimal clearing on site.
Swift Dam Penstock and Bifurcation Project
T BAILEY, INC. fabricated and installed approx. 230 lf of 16′ diameter penstock that began with a complex square to round transition to connect to an existing point and ended in a bifurcation that split into approx. 200 lf of 11′ diameter penstock that connected to two existing points already encased in concrete.
Aberfeldie Bifurcation – BC Hydro
T BAILEY, INC. received the 2009 STI/SPFA Pipe Fabrication Award for the fabrication, finish painting, and delivery of 4 each bifurcations and 900 lf of large diameter steel penstock for the Aberfeldie Redevelopment Project in Cranbrook, BC. The fabricated pieces received a 2 coat epoxy interior coating and the exterior received 1 coat of epoxy and 1 coat of urethane.
Education Hill & Perrigo Upgrades – Redmond, WA
Tank improvements to 3 existing water reservoirs including ladders, platforms, roof vents, shell stiffeners (pictured above), piping, and interior and exterior concrete foundation improvements.
Covington Tank Rehabilitation
T BAILEY performed extensive rehabilitation on an existing welded steel water tank including major foundation modifications, removing, seal welding, and replacing the entire roof, adding two additional shell courses, spiral stairs, demolition of an adjacent tank and foundation, and additional tank and site upgrades.
4.2 MG Hazen Reservoir – Renton, WA
The new 4.2MG water reservoir was 80’d x 115’high. T BAILEY, INC. donated the cost to paint a custom logo on the tank for the local high school located next to the tank site.
Coyote Springs II Power Project, Boardman, OR
Fabrication and field erection of a new 18′ diameter x 210′ tall steel single wall stack for the Coyote Springs II Power Project.
Muckleshoot Standpipe – Auburn, WA
915,000 gallon Muckleshoot Standpipe in Auburn, WA constructed in 1996 for Indian Health Services. Upper tank and roof were constructed on the ground and lifted into place.
High Tank #2 – Lynnwood, WA
In 2001 T BAILEY, INC. built the new 74’d x 88’h 3.5MG High Tank #2 (shown above) and a new 150’d x 30’h 3MG Nike tank as well as performed upgrades on two existing water tanks for the Alderwood Water District.
Keahole Combined Cycle Project Stack & Ductwork
T BAILEY, INC. fabricated and erected a new steel stack and bypass duct and silencer.
Hermiston Stack
T BAILEY, INC. fabricated and field-erected a new 18′ diameter x 195′ high welded steel stack at the Hermiston, Oregon Energy Center.
4.2MG Hazen Reservoir Foundation – Renton, WA
The new 80’diameter x 115’h 4.2MG water tank sat on a 110′ diameter x 4.5′ thick mat foundation with a 5.5′ tall ringwall. The foundation contained over 1800 cy of concrete, 147 tons of rebar and 86 each 2 1/2" diameter anchor bolts. The project had a total of 7000 cy of mass excavation to accommodate the new foundation and detention pond.
Boulevard Road Reservoir Foundation Olympia, WA
Project included demolition/removal of an existing standpipe and construction of a new 2.5MG water reservoir, foundation, associated site earthwork/grading, utilities, electrical, telemetry, etc. The new foundation consisted of approximately 1000 cy of concrete to form a 87’ diameter mat foundation for the reservoir with 76 anchor bolts and approximately 144,000 lbs. of steel reinforcement.
Maple Ridge Highlands Pump Station – Maple Valley, WA
T BAILEY, INC. built a new Pump Station for the private developer of the Maple RIdge Highlands to go along with the new 4Mg Water Reservoir and .5MG Standpipe.
Fire Training Facility – NAS Whidbey, WA
Construction of a firefighting training facility including site work, structural steel mock-up, high temperature resistant concrete pads, control building, jet fuel fire simulation system, and electrical work.
Conoco Phillips Water Injection Storage Tanks
T BAILEY, INC. fabricated, finish painted and delivered 2 each 12’d x 32’l 660 BBL API 650 storage tanks for ConocoPhillips Beluga Gasfield in Alaska. The tanks were finish painted with a 3 coat epoxy interior and a 2 coat epoxy exterior system.
Blair Lakes Complex Fuel & Water Tanks – Eielson AFB, AK
T BAILEY, INC. designed, fabricated, erected, painted, and installed cathodic protection and insulation on (1) 90,000 gallon water tank and (2) 125,000 gallon fuel tanks. In addition we provided and installed supply, distribution, and interconnecting mechanical fuel piping and equipment.
M-I Swaco – Deadhorse, AK
T BAILEY, INC. fabricated, finish painted, and delivered four each 11’-6” Dia. x 30’-10” long ASME Code pressure vessels for drilling fluid storage.
Golden Crossing Casing
T BAILEY, INC fabricated and delivered over 4000 lf of 99” OD x 0.787” bridge piling for the new Golden Crossing Bridge project in Langley, BC.
13 Each STI F921 Double Wall Fuel Tanks
T BAILEY, INC. fabricated and delivered 13 each 20,000 gallon STI F921 double wall fuel storage tanks for the US Navy’s facility in Bremerton, WA.
Barge Load Out Location
The map above depicts our March Point Road Steel Fabrication Shop in proximity to our Barge Load Out Facility.
BC Hydro Aberfeldie Redevelopment Project
T BAILEY, INC. received the 2009 STI/SPFA Pipe Fabrication Award for the fabrication, finish painting, and delivery of 4 each bifurcations and 900 lf of large diameter steel penstock for the Aberfeldie Redevelopment Project in Cranbrook BC.
North West Arctic Borough Fuel Tanks
T BAILEY, INC. fabricated, finish painted and delivered 2 each 50,000-gallon fuel tanks that were 12’d x 59’6” long and 1 each 12,000 gallon 8’d x 35′ long UL142 double wall skid mounted welded steel diesel bulk fuel storage tanks. The exteriors of the tanks received a 3 coat finish paint system of zinc primer, epoxy, and urethane.
Queen Anne Reservoir – Seattle, WA
Steel Tank Institute’s 2008 Tank of the Year Award Winning project! The new foundation consisted of 22 ½ tons of rebar and 550 cy of 4000 psi ready-mix concrete to anchor the new 75’ diameter x 61’ shell high (77’ overall height, including the knuckle and roof) 2MG water reservoir. The reservoir features extensive architectural detailing including 8 main pilasters and 16 secondary pilasters and both upper and lower halos. These architectural details were added solely to provide the owner’s desired visual effect. The tank has a prominent location atop the historic hill and is visible throughout much of the city.
Penstock- Klamath Irrigation District
T BAILEY, INC. fabricated, coated and delivered approximately 786 LF of 119” diameter ½” thick steel pipe in various lengths ranging from 5’ L – 43’ L, including 3 elbow sections, 12 ring girders, 24 slide bearing / fixed bearing supports, trash rack structure and 215’ of catwalk.
Above Ground Storage Tank Project – Log Cabin Road, Olympia, WA
T BAILEY operated as the general contractor to construct a 5.2M gallon AWWA water reservoir for the City of Olympia. This turn-key project included designing, shop fabricating steel, and field erecting an 80’ diameter x 144’ tall welded steel water tank reservoir with a self-supported domed roof.
Testimonials
"T BAILEY is the single-most professional group I have worked with in a subcontracted situation – ever. I was impressed by T BAILEY's ability to do exactly what was committed to be done...you've raised the bar.”