Water System Improvement Project – Vale, Oregon

Water System Improvement Project – Vale, Oregon

T BAILEY, INC. fabricated, coated and delivered approximately 786 LF of 119” diameter ½” thick steel pipe in various lengths ranging from 5’ L – 43’ L, including 3 elbow sections, 12 ring girders, 24 slide bearing / fixed bearing supports, trash rack structure and 215’ of catwalk.

Read Article

USACE Centralized Fueling Station – Yakima, WA

T BAILEY, INC. performed site development including fuel containment and underground utilities to accommodate 3 new API 650 fuel tanks and 2 UL 142 fuel tanks.

Read Article

North Water Reservoir – Gig Harbor, WA

A 2006 Steel Tank Institute Tank of the Year Award-winning 160’ft high x 53’d welded steel water tank with a self-supported seal welded knuckle roof. The site was located in a new housing development and had very limited access and the developer requested minimal clearing on site.

Read Article

4.2MG Hazen Reservoir Foundation – Renton, WA

The new 80’diameter x 115’h 4.2MG water tank sat on a 110′ diameter x 4.5′ thick mat foundation with a 5.5′ tall ringwall. The foundation contained over 1800 cy of concrete, 147 tons of rebar and 86 each 2 1/2" diameter anchor bolts. The project had a total of 7000 cy of mass excavation to accommodate the new foundation and detention pond.

Read Article

Boulevard Road Reservoir Foundation Olympia, WA

Project included demolition/removal of an existing standpipe and construction of a new 2.5MG water reservoir, foundation, associated site earthwork/grading, utilities, electrical, telemetry, etc. The new foundation consisted of approximately 1000 cy of concrete to form a 87’ diameter mat foundation for the reservoir with 76 anchor bolts and approximately 144,000 lbs. of steel reinforcement.

Read Article

Maple Ridge Highlands Pump Station – Maple Valley, WA

T BAILEY, INC. built a new Pump Station for the private developer of the Maple RIdge Highlands to go along with the new 4Mg Water Reservoir and .5MG Standpipe.

Read Article

Fire Training Facility – NAS Whidbey, WA

Construction of a firefighting training facility including site work, structural steel mock-up, high temperature resistant concrete pads, control building, jet fuel fire simulation system, and electrical work.

Read Article

Queen Anne Reservoir – Seattle, WA

Steel Tank Institute’s 2008 Tank of the Year Award Winning project! The new foundation consisted of 22 ½ tons of rebar and 550 cy of 4000 psi ready-mix concrete to anchor the new 75’ diameter x 61’ shell high (77’ overall height, including the knuckle and roof) 2MG water reservoir. The reservoir features extensive architectural detailing including 8 main pilasters and 16 secondary pilasters and both upper and lower halos. These architectural details were added solely to provide the owner’s desired visual effect. The tank has a prominent location atop the historic hill and is visible throughout much of the city.

Read Article

Above Ground Storage Tank Project – Log Cabin Road, Olympia, WA

T BAILEY operated as the general contractor to construct a 5.2M gallon AWWA water reservoir for the City of Olympia. This turn-key project included designing, shop fabricating steel, and field erecting an 80’ diameter x 144’ tall welded steel water tank reservoir with a self-supported domed roof.